NPA asks contractors to hasten repair work on Lagos ports roads

NPA asks contractors to hasten repair work on Lagos ports roads

The Nigerian Ports  Authority (NPA) has appealed to the contractors handling ongoing repairs on the two major arteries into the ports in Lagos, the Apapa-Oshodi Expressway and the Leventis Bridge on the Apapa-Wharf Road, to hasten the repair works in order to ease movement of trucks in and out of the port.

NPA also appealed to the Lagos State Government to support it in clearing up the traders that are occupying nearly half of the newly constructed roads in order to free up the port access roads.

Speaking on Wednesday in Lagos after the tour of Apapa/Tin-Can/ Mile 2 access roads to the port, NPA Managing Director, Mohammed Bello-Koko, called on Buildwell Construction and HITECH Construction, contractors in charge of works on the Leventis Bridge and Apapa-Oshodi Expressway respectively, to work round the clock to see to the early completion of the roads.

According to him, the opening of the Leventis Bridge is critical because shutting it down to traffic has started affecting port operations.

He said the ports have started witnessing a longer waiting time for vessels, a longer dwell time of cargo at the port and the cost of transportation has also gone up because of the shutdown.

“With the closure of the Leventis Bridge, everything is almost at a standstill. This road is critical to the economy and the nation at large. We understand the importance of closing the bridge around Leventis for repair to avoid a collapse but it is seriously impacting port operation,” Bello-Koko said.

He said the situation was due to the fact that Western Avenue has been the major means of movement of cargo into both Tin-Can and Apapa Ports since 2021 when the Cele/Mile 2/Sunrise end of the Apapa-Oshodi Expressway was closed to traffic for construction.

He however said that NPA has been able to get the commitment of HITECH to deliver the first section of the road from Sunrise to Mile 2 by the end of October before continuing with the second section.

On the security concerns discouraging the contractors from working at night, he said the NPA has gotten the commitment of AIG Maritime and plans to also speak with other security agencies to provide security for the contractors to work at night.

A representative of HITECH, Robert Turnor, said that issue of insecurity has been a challenge to workers and property on the site, thereby limiting work at night.