Apapa-Oshodi expressway ready in 10 months, says FG

Apapa-Oshodi expressway ready in 10 months, says FG

 

The Federal Government has said that the ongoing reconstruction and rehabilitation of the Apapa-Oshodi-Oworonsoki-Ojota expressway will be completed within in the next months.

The Federal Controller of Works in Lagos, Olukayode Popoola, announced this on Saturday during a joint inspection of the project with officials of the Nigerian Ports Authority (NPA).

He assured that section one of the project would be completed within three weeks and opened for use afterwards.

“We will complete the remaining portion within the next three weeks, especially the asphalt work.

“So within that three weeks, the outstanding works will be completed fully and then the section one will be made available to the motorists.

“We also complained about the trucks that are infiltrating the road while we are working. We have told them (NPA) that we cannot allow trucks to flock onto the section where we are working because they will disturb the contractor.

“So the trucks will now be monitored and controlled fully. Both the NPA security, the Nigerian Police, LASTMA and then the contractor’s representative will form a synergy to work out how they will be controlling the trucks that enter into the port road henceforth,” he said.

Popoola also said work on sections three and four had progressed, with over 70 percent completion reached cumulatively.

On her part, Hadiza Bala Usman, managing director of NPA, noted that agreements were reached on timelines for construction works in order not to disrupt port operations.

She said discussions were ongoing with the Lagos State Government on how to prevent miscreants from extorting truck drivers, removing shanties and illegal structures along the port corridors.

The rehabilitation of the road started in November 2018. The contract was awarded to AG Dangote Construction Company Ltd at the cost of N73 billion under the tax credit scheme of the Federal Government.